Where the cost sits, team by team
Data
Reporting and regulatory feeds · 12 engineers
against $23,512 average of the prior 3 months
$27,258
$2,272 per engineer in Oct
What is driving it
Measured against the departmental position
- 15%
Refinement quality
of items entered development without agreed acceptance criteria
- 1.4
WIP per engineer
against a departmental average of 1.9
- 43 days
Rework
spent redoing work already called done
- 6 days
Median cycle time
against 9 days across the department
Most expensive items in Data
Open one to see its arithmetic
| Item | Cost | |||
|---|---|---|---|---|
Balance stale after transfer DAT-6745·Defect | 6d | - | 4.4d | $2,288 |
FX rate rounds the wrong way DAT-6825·Defect· no acceptance criteria | 11d | +2d | 4.1d | $2,234 |
Payee nickname lost on edit (EU entity) DAT-6505·Defect· no acceptance criteria | 10d | +1d | 3.9d | $2,124 |
Payee nickname lost on edit (EU entity) DAT-6587·Defect· no acceptance criteria | 11d | +2d | 3.8d | $2,107 |
Push notification sent twice (SME book) DAT-6665·Defect | 7d | - | 3.6d | $1,872 |
55 items completed in Data in October 2026. The five above account for 39% of its cost of delay.