By team
Where the cost sits, team by team
Mobile
iOS and Android apps · 14 engineers
against $44,434 average of the prior 3 months
$41,402
$2,957 per engineer in Sep
What is driving it
Measured against the departmental position
- 18%
Refinement quality
of items entered development without agreed acceptance criteria
- 1.5
WIP per engineer
against a departmental average of 1.9
- 30 days
Rework
spent redoing work already called done
- 7 days
Median cycle time
against 9 days across the department
Most expensive items in Mobile
Open one to see its arithmetic
| Item | Cost | |||
|---|---|---|---|---|
Third party supplier register MOB-6174·Compliance· no acceptance criteria | 26d | +17d | - | $4,267 |
Transaction monitoring thresholds (wave 2) MOB-6388·Compliance· no acceptance criteria | 27d | +18d | 2.7d | $4,122 |
Third party supplier register (phase 2) MOB-6110·Compliance | 20d | +11d | - | $2,684 |
In-app dispute raising (phase 2) MOB-6230·Feature· no acceptance criteria | 18d | +9d | 2.7d | $2,385 |
Vulnerable customer flagging (wave 1) MOB-6138·Compliance | 18d | +9d | - | $2,259 |
67 items completed in Mobile in September 2026. The five above account for 38% of its cost of delay.